a
Should Be Your Demolition
Fast Forward Home
Contractor!
_
Fast Forward - Past Performance!

DEMOLITION:
In Confined Spaces
“Everything had go just right!
If anyone is late,
the entire project misses
the Grand Opening”

Apple Computer Store
3rd Street Promenade
Santa Monica, CA

 
Apple Computer Store:
3rd Street Promenade, Santa Monica, CA
...Located on 3rd Street Promenade in the heart of the Santa Monica, a prime shopping and tourist area, there was no closing the street or sidewalks to the pdedestrians.
Project Details:
General Contractor: DPR Construction
Contact: Doug Allen, (949) 253-0017
Project Date: Start - March - 2003
Completion Date - July - 2003
Completed - On Schedule, On budget
Contract Value: $59,807
Contract Type: Fixed Price
Job Highlights:
Extremely tight, unchangeable deadlines;
All work had to be performed from within the building itself;
Only one small doorway was available to move
all equipnment, materials, and men through;
Simultaneous demolition and construction;
Jobsite was in the middle of a pedestrian zone;
Unknown existing building structures;
Pedestrians will be walking right up against the site;
No room for heavy equipment;
Restricted work hours.
 
Fast Forward was up for the job...

This building, built in 1955, had a long history, it's last configuration as a clothing store. There was a large concrete foundation covering the entire first floor. In the back third, there was a second story with storage and offices. In 1955 you could use virtually any kind of building material including asbestos. The building codes were not nearly as strict as they are today. There were not even current building plans to work from. Grand opening plans were alreay in process, and the entire construction schedule was tight. Schedule slippage on any step, by any one of the many contractors, including Fast Forward, put the whole project in jeopardy of missing the grand opening. Because of this tight schedule, demolition and construction work began simultaneously.
Fast Forward Met These Challenges!

The job involved several aspects of demolition. Each layer had to be peeled away to expose what was underneath. The thickness of the foundation or where pipes were located was not even known.The old floor tile covering the entire ground floor had an asbestos base. Fast Forward coordinated with the hazardous abatement subcontractor to remove the tiles. Further complicating matters, asbestos was discovered in some of the ceiling tiles, and insulation issues with the heating and air conditioning (HVAC) Insulation.

The project, located in a prime shopping and tourist area in Santa Monica, the 3rd Street Promenade, complicated the situation. Work started by erecting a protective barrier that extended out far enough to provide a safe working area in front of the building, while not interfering with the flow of foot traffic. There was no closing the street or sidewalks. Safety for both the public and the work crew was paramount. The city imposed other restrictions. Work hours were designated from 8:00 AM to 3:30 PM, equipment was not allowed in or out via the front; the alley in back was to remain accessible to surrounding businesses.

Once all the hazardous materials were removed, Fast Forward began gutting the remaining building. The façade on the front had to be removed piecemeal. After the front signs were removed, the remainder of the façade was removed, layer by layer, back to the brick structure. Several layers of various ceramic materials were encountered, each chipping appart differently.

 
Extreme care had to be applied to removing the front facade. Tarps were used to catch any chips or fragments from landing on the sidealk below.
 

No chances could be taken that a chip may fly out and injure someone. The entire front of the building was covered with tarps. All work was performed under the tarps in the hot sun. Jack hammers and chipping guns were used in the confined space, while working on mobile scaffolding, to chip away the facade in a carefully controlled process. Not a single piece of the façade ended up outside the protective perimeter. Supervisors were on site at all times to make sure the demolition efforts were well coordinated with construction. Even with both teams simultaneously onsite, no work site injuries occurred while Fast Forward was on the project.

The interior was to be completely repartitioned, so the insides were gutted without altering or damaging the existing superstructure. In addition, the existing heating and air conditioning (HVAC) ducting and equipment was removed without damaging any of the ceiling framing. Each unit and the duct work was carefully disassembled, and one piece at a time, lowered and removed. All interior lighting, stairways and office finishing were to be removed. In addition, the lighting in the building was so old the fixtures had to be treated as hazardous waste. Fast Forward met these challenges without any site contamination.

 
The concrete foundation had to be carefully sawcut to separate it from the city sidewalk without any damage to city property.
 

At this point, the interior foundation was carefully sawcut from the street sidewalk leaving a clean edge to city property. The front four fifths of the foundation was removed in small sections to allow construction efforts to continue at the same time. Moving large blocks of cut concrete, and other debris posed special safety concerns. Utilizing both supervisory personnel and additional coordination personnel, Fast Forward completed the process in a timely manner, with no onsite incidents.

The city of Santa Monica's permit process requires mandatory recycling. There were no onsite space to make scrap piles, no place to bring in large refuse hauling trucks, and only one small doorway to move men and equipment and materials through. Essentially, all equipment and supplies

 
All construction demolition equipment, materials and debris had to be moved through this small single passage, simultaneously at many times!
 

for both demolition and construciton had to be inside the building at all times! Fast Forward overcame all of these diffculties by moving all demolition materials to a 40 yard bin tucked into the corner of the alley. The debris was then hauled to an offsite facility where the materials were sorted for recycling.
Everything on this project was controlled to the smallest detail to meet the time requirement established by the owner in order to make their grand opening date, which could not be extended. Fast Forward met all the deadlines, avoided any damage to surrounding properties, prevented onsite injuries, met all the items specified in the contract requirements, managed all of the material recycling and hazardous waste disposal. All On Budget and All On Time!

 
All Fast Forward demolition equipment is equipped with sophisticated operator safeguards and is operated under close supervision.

 
Should Be Your Demolition Contractor!

Fast Forward, a family-owned corporation, has been in business since 1990. Our customers appreciate our excellent equipment, well trained, highly competent people, safe work practices, close supervision and highly competitive prices. We take care of all these crucial items so you don't spend time worrying about them. That means you'll have more time to manage your business. Want more time to manage your business?

Fast Forward - We make your demolition job easier!

CALL US TODAY FOR
ESTIMATES ON
YOUR NEXT JOB

Also ask us about our Concrete Cutting, Core Drilling, Flat Sawing, Wall Sawing, Interior Stripouts as well as Roll-Off Bins.
 
So, Call us today at
(800) 648-6469
fax: (818) 778-1895

or
info@fast-forward.net
National Association of Demolition ContractorsNational Association of Demolition Contractors
Fast Forward Home Page

Copyright © 2003 Fast Forward Concrete Cutting, Inc.
All Rights Reserved