a
Should Be Your Demolition
Fast Forward Home
Contractor!
_
Fast Forward - Past Performance!

DEMOLITION:

...broke and hauled 3500 square feet of concrete every day. In order to accomplish this feat, they modified a piece of equipment to form a custom ripper/slab grab attachment...

Galaxy Parking Structure Renovation

 

Adhering to the attitude, "whatever it takes", Fast Forward customized a ripper/slab grabber. "The Claw" was designed to get the job done in half the time.

Project Details:
General Contractor: PCL Construction Services
Contact: Steve Witt, Superintendent
Project Date: Start - August 2005
Completion Date - December 2005
Completed - On Schedule, On budget
Contract Value: $780,000
Contract Type: Fixed Price
Job Highlights:
Innovative customization of equipment to create "the Claw" specifically for this job.
Tight schedule imposed by owner.
Limited site access.
Expanded safety requirements to protect the general public.
Kept on schedule working with the general contractor while they poured new concrete.
Saved 50% time and labor on project.
Kept debris stockpile neat and safe.
Vigilant with traffic control topside.
Fast Forward had a "whatever it takes" attitude to get job done on time and on budget.

 

...project was loaded with exceedingly difficult demolition requirements.

CIM Group hired PCL, the general contractor, to renovate the Galaxy parking structure on Sycamore Avenue near Hollywood Blvd. in Hollywood. This project was loaded with exceedingly difficult demolition requirements. Fast Forward took up the challenge with an innovative spirit and determination to maintain the tight schedule imposed by the owner. The demolition portion of the job was roughly 25% of the entire project.

Fast Forward views the relationship between the general contractor and themselves as a partnership. This forms a bond of integrity and trust between Fast Forward management and the contractor and optimizes the attitude of the staff on site to produce high quality workmanship and safety on the job.

The 162,000 square foot slab on metal deck (Robertson decking) had serious concrete cracking problems which needed to be addressed. The existing concrete was reinforced with wire mesh. It was replaced with ½" rebar 12" on center each way with new concrete poured back in.

 
One of the "bays" or sections. Each section or bay is cleaned and made ready for the general contractor to pour new concrete.
 

The project was divided into "bays" or sections. Fast Forward removed every other section, and PCL followed behind pouring the new concrete and letting it set up. They worked around the perimeter toward the center. The center was a bigger area and more wide open so a larger area could be completed in a day. Teamwork and coordination between PCL and Fast Forward were essential elements toward getting the work done in a timely manner.

Fast Forward cut, broke and hauled 3500 square feet of concrete every day. In order to accomplish this feat, they modified a piece of equipment to form a custom ripper/slab grab attachment referred to as "the claw." In lieu of the need to use many jackhammers on the job, the ripper/slab grabber saved approximately 50% time and labor.

 
Working in tight quarters, there was no space for large debris trucks. Broken material was loaded onto trailers pulled by small pickup trucks.
 

Fast Forward used a four step process to complete the work: (1) sawcut a border 3-1/2" deep, locate laps for flutes which meant going to the floor below, and cut 5-1/2". (2) pre-break concrete over beams; (3) "Claw" the concrete making sure not to break through the flutes; and (4) load the concrete onto 5 x 8 dump trailers to accommodate low ceiling height. They then removed the loads from the structure, where they were stockpiled and loaded onto roughly five semis per day.

 
Entrance and exit of site were limited in height. This required Fast Forward to remove debris in pickup trucks with trailers to unload the debris by hand into external stockpile.
 
Exterior stockpile carefully placed in a load out area, and kept neat and clear throughout entire job cycle.
 
Debris removed from stocked piles and loaded into semi trucks, while water is sprayed onto the truck to control dust. Attention to traffic control in the transfer area was strictly enforced for public safety.
 

PCL's superindent on this project was impressed by the integrity of Fast Forward's commitment to getting the job done right. He pointed to four areas where Fast Forward excelled. (1) Fast Forward was considerate to the public while working in an occupied structure; (2) Fast Forward is strong on safety; (3) Fast Forward created the ripper idea which enabled the general contractor to comfortably assure the owner they would complete on time; and (4) Fast Forward stayed aware of the tight schedule and did "whatever it took" (even overtime) to stay on track.

The PCL Superintendent said he would wholeheartedly use Fast Forward in the future.

All Fast Forward demolition equipment is equipped with sophisticated operator safeguards and is operated under close supervision.

 
Should Be Your Demolition Contractor!

Fast Forward, a family-owned corporation, has been in business since 1990. Our customers appreciate our excellent equipment, well-trained, highly competent people, safe work practices, close supervision and highly competitive prices. We take care of all these crucial items so you don’t spend time worrying about them. That means you’ll have more time to manage your business.

Fast Forward - We make your demolition job easier!

CALL US TODAY FOR
ESTIMATES ON
YOUR NEXT JOB

Also ask us about our Concrete Cutting, Core Drilling, Flat Sawing, Wall Sawing, Interior Stripouts as well as Roll-Off Bins.
 
Call us today at
(800) 648-6469
fax: (818) 778-1895

or
info@fast-forward.net
National Association of Demolition ContractorsNational Association of Demolition Contractors
Fast Forward Home Page

Copyright © 2003 Fast Forward Concrete Cutting, Inc.
All Rights Reserved